396 Broadway – Project Update

396 Broadway – Project Update

  • Roof steel phase 1 completed
  • Concrete roof deck – 50% poured. Next half to be poured late next week.
  • Sub cellar bench areas between CL 4 – 8 completed
  • Continue underpinning demo and typical underpinning at elevator pits
  • Continue to install column line 10 steel floors 9 – 2
  • Continue carpentry layouts and remedial work
  • Electrician installing panels and risers

2017-05-30T11:58:24-04:00 May 30th, 2017|