396 Broadway – Rinaldi Better Building – Roof Demolition + Other Updates

396 Broadway – Rinaldi Better Building – Roof Demolition + Other Updates

The following are updates on work being performed at 396 Broadway New York, NY.

• Roof demolition work (phase 1 completed)
• Roof steel phase 1 being installed this week.
• Install first layer of roofing (Phase 1&2) two weeks out
• Lobby Concrete slab completed
• Pour sub grade slab between columns 3 & 8
• Start framing out sub cellar bench areas
• Start underpinning demo and typical underpinning at elevator pits
• Install column line 10 steel floors 9 – 2
• Carpentry layouts and remedial work floors 5 – 8
• Electrician installing panels and risers

More information on the Rinaldi Group project at 396 Broadway…

2017-04-24T17:02:25-04:00 April 24th, 2017|