396 Broadway – Roof Update

396 Broadway – Roof Update

• Completing roof steel phase 1
• Install first layer of roofing (Phase 1) one week out
• Sub grade slab between columns 3 & 8 completed
• Start framing out sub cellar bench areas
• Continue underpinning demo and typical underpinning at elevator pits
• Continue to install column line 10 steel floors 9 – 2
• Continue carpentry layouts and remedial work floors 5 – 8
• Electrician installing panels and risers

2017-05-08T11:56:51-04:00 May 8th, 2017|